Meineke Renovation Project

Meineke Renovation Project

July 11, 2025

Update: 07/11/2025

Meineke Recreation Center Modified Schedule on Tuesday, July 15 

As part of the ongoing renovations at Meineke Recreation Center, crane activity is scheduled between 8 a.m. and 3 p.m. on Tuesday, July 15. To help ensure everyone’s safety during this time, we’ll be adjusting our opening schedule for the facility and pool. Please note that open swim hours will remain unchanged. See the modified schedule below for details.

Meineke Recreation Center Hours On Tuesday, July 15 Are:

Fitness Center: Delayed opening at 10:30 a.m.

Lap Swim: Delayed start time of 10:30 a.m. and ends at 11:45 a.m.

Open Swim: Normal Hours

Aqua Fitness & Barracudas: Cancelled

Gymnasium: Delayed opening at 3 p.m.

Regular Summer Hours Are:

Meineke Recreation Center: Monday to Friday, 5:30 a.m.-9 p.m. | Saturday and Sunday, 6 a.m.-8 p.m.

Meineke Pool: Monday to Friday, 12 p.m.-8 p.m. |  Saturday and Sunday, 11 a.m.-8 p.m. (Closes for the season on Sunday, August 10).

____________________________________________________________________________

Update: 07/3/2025

Meineke Recreation Center and Meineke Pool will reopen on Friday, July 4! 

Meineke Recreation Center and Meineke Pool will officially reopen with special holiday hours on Friday, July 4. We can't wait to welcome you back!

July 4 (Independence Day) Holiday Hours Are:

• Meineke Recreation Center: 8 a.m.-6 p.m.

• Meineke Pool: 12 p.m.-6 p.m.

Regular Summer Hours Are:

• Meineke Recreation Center: Monday to Friday, 5:30 a.m.-9 p.m. | Saturday and Sunday, 6 a.m.-8 p.m.

• Meineke Pool: Monday to Friday, 12 p.m.-8 p.m. |  Saturday and Sunday, 11 a.m.-8 p.m.

____________________________________________________________________________

Update: 07/2/2025

Meineke Recreation Center and Meineke Pool Are Scheduled To Reopen July 4!

Thank you for your continued patience as we work toward safely reopening the Meineke Recreation Center and Meineke Pool.

We are currently scheduled to reopen the facility and pool on Friday, July 4, with Independence Day holiday hours, pending the completion of ongoing utility work. Our team is working closely with utility providers to reconnect the necessary gas and electrical lines required to fully restore building operations, including heated showers at the pool and temporary cooling systems inside the facility.

If any delays occur, we will send another communication. We appreciate your understanding and look forward to welcoming you back soon!

July 4 (Independence Day) Holiday Hours Are:

• Meineke Recreation Center: 8 a.m.-6 p.m.

• Meineke Pool: 12 p.m.-6 p.m.

Regular Summer Hours Are:

• Meineke Recreation Center: Monday to Friday, 5:30 a.m.-9 p.m. | Saturday and Sunday, 6 a.m.-8 p.m.

• Meineke Pool: Monday to Friday, 12 p.m.-8 p.m. |  Saturday and Sunday, 11 a.m.-8 p.m.

____________________________________________________________________________

Update: 06/26/2025

Meineke Recreation Center and Meineke Pool Tentative Reopening

Thank you for your continued patience as we work to safely reopen the Meineke Recreation Center and Meineke Pool following the unexpected closure. At this time, restoration efforts are actively underway. Utility crews are on site replacing damaged underground gas lines, which are necessary to restore heated showers and water at the pool. Additionally, crews are working to reinstall temporary cooling equipment for the building.

If work continues to progress on schedule, we are hopeful the facility could reopen mid-next week, with the pool potentially reopening shortly thereafter. Please note that this timeline is subject to change based on the progress of repairs and final inspections.

We know how important Meineke Recreation Center is to our community, and we’re doing everything we can to get the facility and pool safely back open as soon as possible. We’ll continue to share updates as they become available.

Members may continue to use our other park district facilities during this closure:

In addition to normal lap swim hours at The Water Works and Schaumburg Tennis Plus, lap swim is now temporarily available at Bock Pool from 7 to 9 a.m. during this closure.

____________________________________________________________________________

Update: 06/24/2025

Temporary Closure: Meineke Recreation Center and Pool

Due to a contained fire on the outside of the building on Monday, June 23, Meineke Recreation Center and the Meineke Pool will be closed until further notice. Members may use other park district facilities during the closure.

____________________________________________________________________________

Update: 06/9/2025

Temporary Fitness Access for Meineke Standard Fitness Members

During the renovation of Meineke Recreation Center, Meineke Standard Fitness members will receive temporary access to the fitness center at the Community Recreation Center (CRC). This added access will remain available throughout the renovation period to members maintain their fitness routine without interruption.

 

No action is needed—these memberships have already been updated to allow entry at the CRC. Meineke Standard Fitness members can scan their membership card at the scanners located outside the CRC fitness center doors.

 

Please note: The fitness center at Meineke Recreation Center will remain open during renovations.

 

If you have any questions, please call 847-985-2143. We appreciate your flexibility!

____________________________________________________________________________

Update: 06/6/2025

Meineke Recreation Center Delayed Opening on Monday, June 9

Due to construction and for the safety of our patrons, please note Meineke Recreation Center’s adjusted hours for Monday, June 9:

We appreciate your understanding!

____________________________________________________________________________

Update: 05/27/2025

Meineke Recreation Center Renovation: Phase 1 Begins June 5!

We are excited to announce that beginning June 5, Meineke Recreation Center will undergo a multi-phase indoor and outdoor renovation project! The first phase is expected to conclude mid-September. During this time, please take note of the posted signage directing you to separate entrances. Outdoor temporary fencing and indoor temporary walls and partitions will be installed ahead of this construction. For your safety, please take note of all posted signage, avoid restricted areas and follow marked paths. If you have any questions, please call Meineke Recreation Center at 847-985-2143.

Phase 1 Timeframe:

June 5 to mid-September

Entrance Changes During Renovation:

Fitness Center & Pool: The parking lot entrance (Entrance A) will be used exclusively for admittance to the fitness center and pool.

Gymnasium & Elevator: Door 3, located on Weathersfield Way (Entrance B), will be used for visitors who need access to the elevator or are using the gymnasium for open gym, programs, group fitness, rentals, etc.

Program Changes/Relocations:

- Drop-In Pickleball: Hours will change based on gymnasium needs. Please call ahead at 847-985-2143 to confirm current hours or visit our other drop-in pickleball locations during this time.

- Registered Activities/Programs (Karate, Dance, Tae Kwon Do, etc.): Please review activities/programs you are registered with on Active to find out if your activity/program has been relocated. For assistance, please call 847-985-2115.

- Open Gym: Hours may change based on usage of the gymnasium for activities, private rentals and more. Please call ahead at 847-985-2143 to confirm current open gym hours or visit our other open gym locations during this time.

- Meineke Pool: Expected to open June 2 with in-season pool hours. Click here for all of our current pool hours.

- Fitness Center: Expected to remain open with regular hours. Click here for all of our current facility hours.

 

Parking:

Parking will remain available at Meineke; affected handicap parking will be relocated to the poolside of the lot. On weekends and after 5 p.m. on weekdays, overflow parking is available at the Jerry Handlon Administration Building, 235 E. Beech Drive (a short walk to Meineke Park).

New features during Phase 1:

• Exterior renovation: Mechanical upgrades, roof replacement, façade improvements.

• Interior renovation: Lobby and corridor renovation, lighting improvement, replacement of HVAC system.

 

Phase 2 is expected to begin in September. More details on Phase 2 will be shared in August. We will continue to update this page periodically as the renovation progresses. Thank you for your support and patience!

Back to News